Pelham Island Bridge Update (September 19, 2012)

Much of the backfill is now in place. Work is proceeding on the end posts, the Texas Rails on both sides of the bridge (the wall above the roadbed), and the utilities. This phase of the work will continue for the rest of September and all of October. The picture below was taken Tuesday afternoon (9-18-12). The brackets on the bridge are to support a work platform.

Continue Reading...
Posted in News

Pelham Island Road Bridge Closing Wednesday

Wayland Patch 6/19/12: Pelham Island Road Bridge Closing Wednesday. The bridge over the Sudbury River on Pelham Island Road will at last close to through traffic on Wednesday, June 20 to allow for a replacement bridge to be constructed. Prepartory work began in February as crews constructed temporary structures to carry utilities over the river during construction. The bridge was originally scheduled to close in late February, but delays in the utility construction project led to the delay in closing the bridge.

Continue Reading...
Posted in News

Bridge Update

When the Pelham Island bridge project started about one dozen years ago, the state prepared contractual documents for an 18 month construction period, and they…

Continue Reading...
Posted in News

Latest Update on Pelham Island Bridge Work

Written by Gary Slep: To Our Patient Neighbors, The bridge project is proceeding but is behind schedule by about three weeks due to the utility…

Continue Reading...
Posted in Announcements

Pelham Island Bridge Update (3/12): Water to be disconnected Tuesday at 8am

Plans are to disconnect the water main for the Pelham Island neighborhood on both sides of the bridge on Tuesday, March 13th, at 8am to…

Continue Reading...
Posted in News

Contractor expects to cut water to Pelham Island Monday

Wayland Patch 3/9/12:  Contractor expects to cut water to Pelham Island Monday.  Contractor Michael Brooks has informed town officials that construction crews are tentatively scheduled to temporarily cut water service Monday to about 65 residents affected by the Pelham Island Road bridge project.

Continue Reading...
Posted in News

Pelham Island Bridge Construction Continues

Wayland Patch 3/6/12: Pelham Island Bridge Construction Continues. Work is proceeding on the Pelham Island Bridge at a good pace. The contractor is in the process of inserting four, 66-foot H-beam pilings into the ground just downstream of the existing bridge to temporarily support the water main and the gas line in preparation for the bridge being replaced. The contractor is using a large crane to insert the steel pilings, which are vibrated into position. Two of the pilings are now in place, reaching down to bedrock. Two concrete foundations have also been poured at the crossing points on both river banks. The process is being overseen by MassDOT District 3 personnel stationed in Worcester.