Wayland Patch 3/6/12: Pelham Island Bridge Construction Continues. Work is proceeding on the Pelham Island Bridge at a good pace. The contractor is in the process of inserting four, 66-foot H-beam pilings into the ground just downstream of the existing bridge to temporarily support the water main and the gas line in preparation for the bridge being replaced. The contractor is using a large crane to insert the steel pilings, which are vibrated into position. Two of the pilings are now in place, reaching down to bedrock. Two concrete foundations have also been poured at the crossing points on both river banks. The process is being overseen by MassDOT District 3 personnel stationed in Worcester.
Copyright © 2023 WaylandeNews - All Rights Reserved.
Please be aware that many links on our site will take you from WaylandeNews. We are not responsible for content on other websites.
Please be aware that many links on our site will take you from WaylandeNews. We are not responsible for content on other websites.